MOLDE, Norway, November 5, 2024 – Axess Group completed the installation and commissioning work for the first FLNG project in the Republic of Congo earlier this year.
The scope of work included mooring and hookup operations, complex rigging activities and electrical completions on the FLNG and FSU. The project commenced at the shipyard in Dubai, UAE, and concluded in the Republic of Congo, spanning a total of 9 months. Subsequently, Axess also supported the client with completion works on its onshore gas pre-treatment plant.
“We are happy to be involved in such a significant LNG project. Our global footprint has been crucial in ensuring the success of the project. Over 140 qualified personnel were deployed from various entities within the Group, including Axess UK, Axess India and Axess Norway. We look forward to continuing our partnerships with the client,” Christiaan Enslin, Regional Manager – Southwest Africa at Axess Group said.
Since 2016, Axess Group has been supporting the client on several other projects in countries including Angola, Ghana and Mexico.